SkyWest Hangar
Boise, idaho
completed 2015
General Contractor: McAlvain Group
Description: The SkyWest Airlines Aircraft Maintenance Hangar is a 135,000 sq ft maintenance facility at the Boise Airport. The 14 acre site encompasses the 101,000 sq ft hangar and 34,000 sq ft of additional shop, office and service spaces. The structure has an 80 ft. roof height with tapered columns, clear-span frames and bay spacing at 25 ft. Clear height within the building is 55 ft. with 45 ft. door clearance. The hangar is the largest pre-manufactured clear-span metal building in the northwest and was completed on a 10-month fast-track schedule.
Total Project Cost: $20 Million
Project Size: 135,000 sf
*images courtesy of SkyWest Airlines & McAlvain Group